Notice of Construction – Bronte Street South

As part of the 2019 Asphalt Overlay program, the Town’s contractor, Associated Paving and Material Ltd., will be resurfacing Bronte Street South. This work will include asphalt removal, road asphalt overlay and finishing works.

Residents may experience some delays when certain construction activities are being performed. There will be some access restrictions to/from various entrances to plazas on Bronte Street South depending on the construction phase. Please follow construction signage and on-site flagman instructions.

Construction will be completed in three phases:

Phase 1:  Northbound, August 19 to 22, 2019 – Access to the east restricted

Phase 2:  Center Line, August 26 to 29, 2019 – Access to the east and west restricted

Phase 3:  Southbound, September 3 to 6, 2019 – Access to the west restricted.

Dates are subject to change due to weather and construction scheduling.

For more information on this project, please see the attached notice.

 

 